Engineering Guide · Survey, ITP, SAT, and Maintenance Checklists

PIDS Installation, Commissioning, and Maintenance: A Project Checklist

Reliable PIDS installation follows clear stage gates: structural survey, sensor mounting, commissioning tests and signed handover. Coordinate equipment supply, civil foundations, mechanical erection, head-end integration and maintenance across the project team, using the selected model manual for installation dimensions and wiring.

Project scope and gate conditions
Lifecycle ResponsibilityTypical Party (Confirmed Per Project Contract)Gate Condition Before Advancing
01 · Equipment supply and product docsPerimSense supplies agreed PIDS hardware BOM, preliminary zone layouts, and model manualsExact model codes, barrier format (TW-100 vs TW-150), and manual revision confirmed on order
02 · Civil footings, walls, and conduitsCivil or fencing contractor executes foundations, wall copings, drainage frames, and cable ductsSurvey defects resolved; concrete cured and conduits proved clear before sensor mounting
03 · Barrier and sensor erectionFencing erector / installer mounts posts, wires/coils, optical cables, or buried/corridor unitsPhysical ITP inspection (#s03) passed—no loose posts or binding wires left to commissioning
04 · Electrical, head-end, and SATSystem Integrator (SI) powers backend units, tunes settings, maps cameras, and leads witnessed testsThreshold re-verification (#s04), fault injection, and baseline log (#s05) signed off at SAT (#s06)
05 · Operations and layered upkeepFacility security and grounds/electrical teams run SOPs, clear zones, and scheduled checksAs-built drawings, baseline settings archive, and 3-layer maintenance plan (#s07) handed over
Fig. 25.1 — Seven-gate PIDS implementation sequence from pre-work survey through ITP physical sign-off, on-site tuning, environmental soak, SAT handover, and three-layer routine maintenance.
Fig. 25.1 — Seven-gate PIDS implementation sequence from pre-work survey through ITP physical sign-off, on-site tuning, environmental soak, SAT handover, and three-layer routine maintenance.

01 — Pre-construction site survey

Log Numbered Sector Conditions and Separate TW-100 vs TW-150 Checks

Walk every boundary sector before civil work starts. Assign sector IDs, attach dated photographs, and resolve any structural, clearance, or drainage defect that would compromise tensioning or detection.

SV-01–SV-06 · Site survey log
Survey Item IDBoundary System ScopeWhat to Inspect and Record on SitePhoto / Drawing RefDefect Found and Remediation OwnerHold-Point Status
SV-01 · Sector geometry, corners, and gatesAll PIDS modelsSector start/end markers, length, grade steps, corner angles, sliding/swing gate widths, and vehicle crossing frequency[Plan / Photo ID][Owner / Civil / Fence Contractor][Open / Cleared]
SV-02 · Parallel taut-wire structural pathPerimTaut TW-100Soil bearing or wall-coping integrity for end/corner anchor posts, intermediate support line, gate-post terminations, and clear wire corridor[Plan / Photo ID][Civil / Structural Engineer][Open / Cleared]
SV-03 · Concertina coil base and force transferPerimTaut TW-150Rigid wall coping or verified fence top rail, coil mounting/tie arrangement, axial load transfer to the 1 internal sensing wire per detector, and maintenance access[Plan / Photo ID][Fence Contractor / PerimSense Review][Open / Cleared]
SV-04 · Host fence, surface, or corridor stateFF / FO / VC / BF / PM / EF / MW / LPMesh tension and loose panels (FO/VC); trench sub-base, drainage, buried utilities, and reviewed waterway depth/flow (BF-300) vs dry land paths (PM-280); flat unobstructed sightline (MW-400/MW-450M)[Plan / Photo ID][Civil / Grounds / SI][Open / Cleared]
SV-05 · Electromagnetic exposure, vegetation, and wildlifeAll PIDS modelsProximity to HV switchgear or electrified rail—where 0 W TW post switches and passive optical fibers operate unaffected by electromagnetic and radio-frequency interference (EMI/RFI)—plus overhanging branches, tall grass, and local wildlife activity[Plan / Photo ID][Grounds / Electrical Eng][Open / Cleared]
SV-06 · Backend room, power, and head-endAll PIDS modelsProtected indoor/enclosure space, AC/DC/PoE availability, earthing bar, conduit lead-in path (24-power-guide.html), camera presets, and existing alarm panel/VMS interface[Plan / Photo ID][SI / Facility Electrical][Open / Cleared]
Fig. 25.2 — Separate pre-installation structural check diagrams: (Left) TW-100 parallel wire anchor, intermediate guide, detector post, and corner/gate interfaces; (Right) TW-150 concertina coil base rigidity, tie points, and axial force transfer to the single internal sensing wire. Exact dimensions follow approved model drawings.
Fig. 25.2 — Separate pre-installation structural check diagrams: (Left) TW-100 parallel wire anchor, intermediate guide, detector post, and corner/gate interfaces; (Right) TW-150 concertina coil base rigidity, tie points, and axial force transfer to the single internal sensing wire. Exact dimensions follow approved model drawings.

02 — Pre-work readiness and delivery stages

Separate Hardware Dispatch from Site Readiness Across Four Stages

Fast equipment manufacturing shortens your critical path only when civil foundations, conduits, permits, and head-end interfaces are ready to receive the hardware. Track four separate delivery stages—and verify the pre-start readiness items before crews mobilize.

Four-stage delivery and readiness
Project StageScope and Key InputsPre-Condition to Enter Next StageResponsibility
Stage 01 · Factory Dispatch ReadinessBOM confirmation, barrier format selection, and factory production/testing (PerimTaut TW-100 and TW-150 support fast factory dispatch once configuration and order are confirmed)Approved order BOM, model manual revision, and shipping consignee details lockedPerimSense + Buyer Procurement
Stage 02 · International Freight and CustomsAir/ocean transit, destination customs clearance, import documentation, and inland haulage to sitePacking list reconciled on arrival; enclosures and reels inspected for transit damage before storageFreight Forwarder / Importer / Buyer
Stage 03 · Civil Works and Physical MountingCured concrete footings/copings, pulled conduits, post erection, wire/coil tensioning or fiber splicing, and indoor backend wiringPre-Commissioning ITP (#s03) signed off with zero unresolved structural or cable defectsCivil / Fence Crew + SI
Stage 04 · Commissioning, Soak, and SATOn-site threshold tuning, pull/cut and fault walk-tests, camera verification check, environmental soak log, and handover trainingWitnessed SAT package (#s06) signed; unseasonable weather items logged for follow-upSI + Facility Operations / Consultant

03 — Pre-commissioning inspection (ITP)

Verify Mounting, Force Transfer, and Wiring Before Touching Any Threshold

Run this Inspection and Test Plan (ITP) sector by sector against approved drawings and the model manual. Verify secure posts, free wire movement, sound connections, and correct splices before powering processors and setting pull thresholds.

Scroll across for all fields; mobile shows labeled records.

ITP · Installation inspection
ITP Item IDPhysical or Electrical CheckReference BasisResult (Pass / Hold / N/A)Sector / Photo RefCorrective Action RequiredRe-Inspection Sign-Off
ITP-01 · Foundations, anchors, and bracketsEnd/corner anchors, wall-coping bolts, TW-150 coil brackets, or microwave posts are plumb, rigid, and fully curedApproved civil/mounting drawing + model manual[Pass / Hold][Sector / Photo][Re-anchor or brace before tensioning][Name / Date]
ITP-02 · Wire tension and clean force transferTW-100 parallel wires or TW-150 internal sensing wire move freely through guides without pinching, snagging, or foliage contactModel installation manual for ordered version[Pass / Hold][Sector / Photo][Clear pinch point / re-tension / trim brush][Name / Date]
ITP-03 · Host fence, grille, or trench finishAttached FO/VC cables tied to tight mesh without slack loops; FF-250 grille frame secure; BF-300/PM-280 bedding reinstatedModel installation manual + civil spec[Pass / Hold][Sector / Photo][Tighten mesh / secure ties / re-bed][Name / Date]
ITP-04 · Enclosures, glands, and splicesDetector post covers, junction boxes, and optical splice closures sealed; minimum bend radius respected; tamper switches seat cleanlyModel enclosure and cable schedule[Pass / Hold][Sector / Photo][Replace seal / re-dress bend / re-splice][Name / Date]
ITP-05 · Power, earthing, surge, and labelsIndoor/cabinet supply voltages verified (P = V × I / ΔV within spec), SPD earthing bonded, and all L1/L2 cables labeled at both endsPage 24 cable/load schedule + site electrical rules[Pass / Hold][Rack / Cab ID][Correct polarity, SPD bond, or missing tags][Name / Date]
ITP-06 · Physical zone-to-camera alignmentPhysical zone start/end posts match control-room zone map names, fence markers, and assigned camera fields of viewApproved zone map and VMS preset schedule[Pass / Hold][Zone ID][Adjust preset angle or update zone label][Name / Date]

04 — On-site adjustable pull threshold and re-verification

Log Pre/Post Pull Threshold Settings and Re-Test Both Contact Filtering and Intrusion Response

PerimTaut TW-100 and TW-150 feature an on-site adjustable pull threshold to filter out animal and plant contact. Follow three commissioning rules whenever pull thresholds are set or changed:

  • 01

    Record Mechanical Pull Settings

    Follow the approved factory commissioning procedure for the supplied model version. Record the on-site adjustable pull threshold as mechanical pull transmitted to the sensing wire and detector.

  • 02

    Joint Re-Verification After Every Change

    Any pull threshold adjustment to filter out animal and plant contact or wind-swayed foliage must be immediately followed by representative pull/spread and simulated-cut tests at the start, middle, and end of the zone to confirm target intrusion detection still passes.

  • 03

    Safe Cut Simulation

    Verify wire or coil cut detection using the manufacturer-approved, site-authorized non-destructive release/test procedure, keeping active barrier wires and coils intact. Record barrier sensing-wire release tests separately from signal-cable open/short fault tests.

Scroll across for all fields; mobile shows labeled records.

TW · Threshold and joint re-verification
Project / Zone IDModel and Manual RevInitial / Adjusted Setting RecordDate, Time, and Site ConditionsApproved Test Method and Positions / TrialsExpected Intrusion or Fault OutputActual Control-Room Display and Camera Call-UpResult (Pass / Hold)Root Cause / Corrective Action and RetestPerformer and Witness Sign-Off
[e.g., Z-A01]TW-100 · [Rev]Pre: [Ref] → Post: [Ref][Date/Time · Wind / Temp / Grass]Controlled pull test at start, mid, end (3 trials each)Zone A01 Intrusion Alarm + Preset P-01[Log timestamp, zone ID, camera view][Pass / Hold][If Hold: fix binding/setting + retest][SI / Owner Rep]
[e.g., Z-A01]TW-100 / TW-150 · [Rev]Post-adjustment active baseline[Date/Time · Ambient state]Authorized non-destructive tension-release (cut simulation)Zone A01 Intrusion/Cut Alarm[Log timestamp and reset check][Pass / Hold][Verify clean mechanical return + retest][SI / Owner Rep]
[e.g., Z-A01]Backend Module · [Rev]Supervised / Tamper loop[Date/Time]Detector cover tamper open + L1-Mech cable disconnect testDistinct Tamper / Line Fault (separate from wire pull)[Log fault channel on head-end][Pass / Hold][Check EOL/wiring mapping + retest][SI / Owner Rep]

05 — System linkage and environmental baseline log

Record Operating Events and Refine Performance

  • 01

    Record Site Test Results

    Log successful detections against valid trials under the recorded conditions, such as 9/9 pulls on Zone A01. Keep the test method, conditions and results together for acceptance and future comparison.

  • 02

    Agree Four Event Categories

    Record (1) Verified Intrusion/Test Events, (2) Environmental or Operational Non-Intrusion Triggers (wind, wildlife, adjacent traffic, staff activity), (3) Equipment/Power/Cable Faults, and (4) Unclassified Events awaiting camera/patrol review. Compare FAR/NAR using consistent denominators, zone lengths, and weather records.

  • 03

    Schedule Seasonal Verification

    Include high winds, heavy storms and peak vegetation growth in the follow-up plan, with observations recorded against the commissioning baseline.

Scroll across for all fields; mobile shows labeled records.

Four-bucket environmental observation log
Observation Window and Active UptimeActual Weather and Site Operations ObservedAlarm Timestamp and Zone / CoordinateEvent Category (Intrusion / Env-Op / Fault / Unclassified)Verification Evidence (Camera Clip / Patrol Note)Responder Action TakenAny Setting Change (Requires #s04 Retest!)Unobserved Conditions / Follow-Up Item
[Start–End Dates · Total Active Hours][e.g., Moderate wind, HV switching, 12 truck gate cycles/day, night patrol][Timestamp · Zone ID or m][Select 1 of 4 categories; keep unknown cause as Unclassified][Camera ID / clip ref / guard report][Dispatched / Logged only / Work order][None, or log old→new + retest ref][e.g., Gale-force wind and monsoon rain check scheduled for Q3]

06 — Site acceptance (SAT) and handover

Complete FAT and SAT Records for Signed Project Handover

Factory inspection verifies hardware before shipping. Site Acceptance Testing (SAT) verifies the installed barrier, field cabling, backup power, camera presets, and operator procedures together on your perimeter. Track remaining actions in the punch list and close them for handover.

SAT · Acceptance and handover
Handover Package ItemRequired Deliverable ContentVerification Status (Accepted / Open Punch Item)Responsible OwnerSign-Off Role
SAT-01 · Project acceptance criteriaAgreed target events, zone/location tolerances, and fault tests matched to contract brief[Accepted / Open]Consultant / Owner SecurityOwner / Consultant
SAT-02 · As-built drawings and cable tagsFinal zone map, post/marker coordinates, L1/L2 cable routes, and enclosure power locations[Accepted / Open]System Integrator + Civil/FenceSI / Facilities
SAT-03 · Baseline configuration archiveFinal on-site TW threshold records, processor software/firmware versions, and backed-up settings[Accepted / Open]System IntegratorSI / Security Ops
SAT-04 · Signed ITP and test logsCompleted #s03 ITP sheets, #s04 pull/cut/fault test logs, and camera preset call-up verification[Accepted / Open]Installer + SIInstaller / SI / Owner
SAT-05 · Soak log and seasonal punch list#s05 operational baseline log plus scheduled follow-up items for unobserved weather/seasons[Accepted / Open]SI + Security OperationsOwner Security
SAT-06 · Manuals, spares, and trainingApproved manuals for supplied model revisions, agreed spare parts, and operator/grounds SOP walkthrough[Accepted / Open]PerimSense (docs/spares per BOM) + SIOwner Facilities / Ops

07 — Three-layer maintenance and symptom troubleshooting

Separate the Low-Upkeep Sensing Core from Routine Barrier and Backend Checks

On PerimTaut TW-100 and TW-150 barriers, core detection operates through the physical properties of its materials—so as long as its protective materials remain intact, the core sensing structure rarely suffers damage and needs minimal routine upkeep. Organize ongoing maintenance across three distinct layers, set check intervals from the product guidance and site exposure (coastal salt, dust, rapid vegetation growth), and always re-run affected zone walk-tests after storm damage, vehicle impact, civil/fence work, or setting changes:

Three-layer maintenance and retest
Maintenance LayerWhat This Layer CoversRoutine Action and Trigger ConditionWhat to Log
Layer 01 · Core Sensing Structure (PerimTaut TW-100 / TW-150)Material-property post sensing mechanism protected by its intact protective materials (0 W post switch)Minimal core upkeep; check protective condition and function after physical impact or severe events using the maintenance guidance.Visible external impact/damage, post-event functional check, and any item escalated to technical support
Layer 02 · External Barrier, Clear Zone, and Ground/Opening HardwareExposed tensioned wires or razor coils, anchor posts, fixings, host mesh (FO/VC), culvert grilles (FF-250), surface cover (BF-300/PM-280), microwave lanes (MW-400), and vegetationTrim vegetation clear of wires/beams, clear culvert debris, inspect coastal/industrial corrosion, repair disturbed soil/paving, and retension wires where instructedSector ID, physical change found, remediation completed, and whether mandatory #s04 zone retesting was triggered
Layer 03 · Powered Backend, Batteries, and Reporting ChainZone modules, controllers, optical/active processors, UPS/standby batteries (MW-450M packs), surge earthing, network switches, and VMS/camera presetsVerify AC-fail/battery autonomy, clean optical connectors if opened, confirm software/setting baseline matches #s06 archive, and test alarm-to-camera handoffPower/comm fault history, standby battery check result, firmware/setting version, and recovery walk-test sign-off

When contacting technical support for an installed system, include six items to speed diagnosis: (1) model code and manual/serial reference, (2) affected zone layout and connected backend hardware, (3) exact symptom and what changed on site beforehand, (4) exported alarm/fault logs, (5) clear site photographs, and (6) checks already run using Figure 25.3.

Fig. 25.3 — Five-step symptom-first troubleshooting sequence: inspect physical site changes, connections, power/comms, and head-end mapping before altering baseline sensor thresholds.
Fig. 25.3 — Five-step symptom-first troubleshooting sequence: inspect physical site changes, connections, power/comms, and head-end mapping before altering baseline sensor thresholds.